Uttarakhand: Indian Railways has achieved a major Tunnel-14 breakthrough in the 6.59-km Rishikesh-Karnaprayag Rail Project. The milestone was achieved on 27 November in Uttarakhand’s Rudraprayag district. It connects two excavated sections, measuring 4.7 km from Portal-1 at Sumerpur and 1.79 km from Portal-2 at Marora.
The construction involved challenging ground conditions at both portals. At Portal-1, engineers excavated a 110-metre stretch of the triple-track tunnel through loose soil beneath inhabited areas. Only 20–30 metres of soil and rock covered this section. Therefore, teams used specialised methods, including pre-excavation and multi-drifting, to ensure safe construction.
Tunnel-14 breakthrough follows specialised safety measures
At Portal-2, construction teams strengthened the slope using micropiles and rock bolts. The work included micropiles extending 30–35 metres deep and rock bolts measuring 15–20 metres in length. In addition, consolidation grouting helped stabilise the ground. These measures enabled the main tunnel drive to begin in March 2024, after teams resolved ground settlement issues at Marora and matters involving land and home acquisition.
Teams also carried out approximately 100 metres of mechanical excavation at Portal-2. Meanwhile, controlled blasting near both portals was restricted to daytime hours to protect nearby settlements. Specialised ventilation systems were installed along the 4.7-km excavation stretch from Portal-1. These systems ensured fresh air circulation and helped regulate the temperature inside the tunnel.
The breakthrough marks significant progress in the Rishikesh-Karnaprayag Rail Project. The railway initiative aims to improve connectivity to Uttarakhand’s hill regions. It is also expected to make travel easier for pilgrims and tourists visiting important destinations. Improved access could further support regional development across the state.