Revanth seeks Chhattisgarh NOC for Sammakka Sagar barrage

Hyderabad: Telangana Chief Minister A. Revanth Reddy has sought a No Objection Certificate (NOC) from Chhattisgarh for the Sammakka Sagar barrage. He urged the neighbouring State to expedite pending clearances and permit water storage in the reservoir. Chhattisgarh Chief Minister Vishnu Deo Sai assured him that officials would complete the NOC process soon.

Revanth Reddy met Sai in Raipur on Tuesday, November 17. Irrigation Minister N. Uttam Kumar Reddy accompanied him. During the meeting, the Telangana Chief Minister explained the State’s growing water needs amid drought conditions linked to El Niño-related weather patterns.

He requested Chhattisgarh to allow water storage in the Sammakka Sagar barrage. He also sought faster approval of the NOC and other pending clearances. Responding positively, Sai assured the Telangana delegation that the process would move forward expeditiously.

The Telangana government initially proposed the project at Kantanapalli. That site would have submerged 11,408 acres and affected 17 Adivasi villages. It would also have affected security infrastructure. Therefore, the government shifted the proposed barrage location to Tupakulagudem to reduce submergence.

IIT study details impact of Sammakka Sagar barrage

An IIT Kharagpur study estimated that the reservoir would submerge around 33 acres in Chhattisgarh at its full reservoir level. Even during heavy floods, the affected area would not exceed 100 acres, according to the study.

At Chhattisgarh’s request, Telangana paid IIT Kharagpur Rs. 9.883 crore in April to conduct the assessment. The institute submitted its report to the Chhattisgarh government on July 30.

The Sammakka Sagar barrage stands across the Godavari at Tupakulagudem in Mulugu district. It has a full reservoir level of +83 metres and a storage capacity of 6.94 TMC. The project aims to use Godavari water for irrigation and drinking needs in drought-prone, backward and tribal regions.

Revanth Reddy reiterated Telangana’s commitment to funding land acquisition, compensation and rehabilitation in Chhattisgarh. He said the State would provide the required funds in line with established norms.

The Chief Minister also pointed out that construction of the barrage had already been completed. He urged Sai to issue the NOC in the larger public interest. He further sought clearance of all remaining approvals without further delay.